HYUNDAI’S U.S. HQ MEETS EXHAUST SHAFT CODES USING AEROSEAL®

Rajeev Nedumaran • July 2, 2022

HYUNDAI U.S. HEADQUARTERS

HYUNDAI’S U.S. HQ MEETS EXHAUST SHAFT CODES USING AEROSEAL

HYUNDAI’S U.S. HQ MEETS EXHAUST SHAFT CODES USING AEROSEAL


The new Hyundai U.S. corporate headquarters was scheduled to open for business in just a few weeks. The finishing touches were being made to the interior of the 6-story, 500,000 sq. ft. building in Fountain Valley, California. No one was happy to learn that building engineers could not get official sign-off for the project because of duct leakage in the structure’s four smoke evacuation shafts and an outside air shaft.


Options for reducing the leakage and getting the shafts to meet code were examined. One option included using spray foam to seal visible leaks in the drywall interiors. But this would take months to accomplish, cost as much as $1,000,000, and there would be no guarantee spray foam would sufficiently reduce leakage. Then another option was found — Aeroseal duct sealing technology. Glumac had used the Aeroseal technology for a similar project in Las Vegas with successful results.


PROJECT OVERVIEW


BUILDING

Hyundai U.S. Headquarters


LOCATION

Fountain Valley, California


AEROSEAL CONTRACTORS

Healthy Homes 4U (a.k.a. Aeroseal West Coast)


CONTRACT ENGINEER

Glumac


GOAL

Meet required duct sealing codes for commercial new construction project


BEFORE AEROSEAL

14,861 CFM of leakage


AFTER AEROSEAL

808 CFM of leakage


RESULTS

95% leakage reduction to meet building code for 5% or less leakage and finish the project on schedule


Options for reducing the leakage and getting the shafts to meet code were examined. One option included using spray foam to seal visible leaks in the drywall interiors. But this would take months to accomplish, cost as much as $1,000,000, and there would be no guarantee spray foam would sufficiently reduce leakage. Then another option was found — Aeroseal duct sealing technology. Glumac had used the Aeroseal technology for a similar project in Las Vegas with successful results.


It took the Aeroseal contractor only a couple of weeks to complete all five shafts. Leakage rates were reduced from 20% to 1.1% – well below current code requirements. The cost was just a fraction of the next lowest cost alternative. Best of all, the work was completed in time and Hyundai’s new U.S. corporate headquarters opened on schedule.

I focus exclusively on healthcare facilities and I think that any one of my clients would have an application for this technology. If this (sealing project) was done manually, it would have potentially taken weeks rather than a couple of days to complete.

-Brian Berg, Engineer of Record, Glumac

To Learn More About Improving The Comfort, Indoor Air Quality, and Energy Efficiency Of Your Building Call 0226759426 or Email info@aeroseal.nz

April 18, 2025
Completing WP2 at Auckland International Airport was a milestone for LIMS Aeroseal. Not only did we help Econair Services Limited meet industry standards for ductwork airtightness, but we also demonstrated the scalability and reliability of Aeroseal technology in high-profile projects.
Two men are standing next to each other in a room in a house under construction.
April 17, 2025
Aeroseal's duct and envelope sealing technologies offer a better way to meet and exceed building codes and performance standards in New Zealand. They’re more effective, easier to apply, and deliver consistent, reliable results, helping you achieve Code Compliance and create energy-efficient, comfortable, and healthy buildings.
December 26, 2024
In New Zealand, the duct sealing industry is expected to evolve significantly in 2025, particularly with the adoption of Aeroseal technology. Here are the key trends and expectations specific to this market:
More Posts